Client: IFM Bolton Ltd
Contract Value: £1.1m
Duration: 3 months on site plus off site manufacture
Contract: JCT Design and Build Contract 2016
KOK Job Reference: 2580.05
QS: ANTHONY BAILEY
CDMA: RUSSELL WORTON
Brief Description of Works:
The works comprised the demolition of existing Contractor Works compound, provision of concrete raft foundations, working around existing services, provision of link corridor to main building and provision of a single storey prefabricated modular building providing 9nr Assessment rooms, 10nr Trolley bays and ancillary facilities.